30 aprile 2010
In room 2 we are still cleaning the collapse US 28 and widening the invastegted area.
We started again the escvation in room 5 removing the layer US 115, a ground floor conected with an attending after the collapse of the stracture (Period IV)
In Area 2 we finished to remove the collapse of the main entrance began yesterday with the escvator cleaning also the ground floor of the entrance; we also start to clean the South wall of the doorway.